Project Server Error Id 9133

Brian. Environment: Project Server 2010 Cause: Confliction in Schedule due to circular relationship. Project: ProjectSchedulingEngineException (9133). We have already used this below code to achieve it, but however after the code executed successfully when we again try to read the custom field dataset of Timesheet, we found useful reference

If that fails then perhaps we can identify what's going wrong if you open a support incident - could be hitting some other bug. Get added task custom fields (DataRowState.Add) 4. Select Personal Settings from the left menu. Please we would appreciate any help in this matter. https://badalratra.wordpress.com/2013/08/18/error-id-9133-or-26000-project-server-2010/

For example, return a message to use Project Professional to change the TASK_OUTLINE_LEVEL. Best regards, Brian Reply ANU says: March 20, 2009 at 9:12 am hi Brian, Thanks for your response!! Can I come to know how could this happen?  Also the following message is showing in the ULS logs: "Leaving Monitored Scope (ExecuteStoredProcedureNoResult -- MSP_WEB_SP_QRY_CUBESTATUS_DeleteStatus). How do I do it?

  1. Best regards, Daniel Wednesday, January 02, 2013 8:40 AM Reply | Quote 0 Sign in to vote Hi Daniel, I would think another workaround to try with: http://www.projectserverhelp.com/Lists/Posts/Post.aspx?List=f884b43f-61db-4c4e-94a3-38f21a8efdad&ID=197&Web=28a89920-6690-45b4-9132-339c2f40a7e7 Another similar thread
  2. Thanks, Dustin

    0 0 05/22/14--13:40: Status Manager bypassed...
  3. Please give me ammunition to convince our management to shift to the server based version?
  4. Unfortunately i can't see any error pattern at the moment, but next week one of our Project consultants will have closer look on these projects.
  5. The same OLAP database was showing as not built.
  6. This custom field represents the key to the task in our system.
  7. Can I create an external content type(BCS) to get the data from Oracle and create a field using that ECT in Project Server?

Did you try the above for the project? The content you requested has been removed. If you can repro with a clean project with known steps I'd love to know. Way to identify the circular relationship in the project plan The single most prevalent cause of circular relationships is links on summary lines.

Project Server Error Code 24006 Error 24006 Microsoft Corporation Microsoft Project 36. Privacy statement  © 2016 Microsoft. I am encountering similar issues and the given SQL query to identify corrupt tasks/projects is not listing the projects where the issue is being encountered currently. No problem, but one slight annoyance - the settings only let you choose between 4:3 and 16:9, which I'm perfectly fine about, the preview shows the film to be widescreen, which

Also, see if you can go back to a previous version of the file before you experienced circular relationship issues. I am looking into a support incident where values are being set for summary tasks (or rather they are not) - these are likely to be read-only if "roll-up" is set, The key will be finding what is special about the tasks that are failing. What should I do?

Following case: The overnight patch changes every time the given permissions. When adding to the PSI, Cost values should be multiplied by 100. For other smaller GANTT's it works really well. Timesheet:bd5335f3-8402-e411-942c-00505694197c [bucketHash:493F1FF2] Exception occured in method 'TimeSheet.ProcessGridUpdates' System.Collections.Generic.KeyNotFoundException:The given key was not present in the dictionary.    at Microsoft.Office.Project.Server.BusinessLayer.Statusing.<>c__DisplayClass42.b__3e(Guid g)    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()    at Microsoft.Office.Project.Server.BusinessLayer.Statusing.SubmitStatusWithResult(Guid resid, Guid[] updateGuids, String comment)    at Microsoft.Office.Project.Server.BusinessLayer.TimesheetSEM.SubmitLinesInternal(IEnumerable`1 lines, String comment)    at Microsoft.Office.Project.Server.DataAccessLayer.ProjectServerDatabaseTransaction.RunInTransaction(ProjectServerDatabaseTransaction transaction,

Thank you very much Mike Reply Brian Smith - MSFT says: February 7, 2008 at 2:29 pm I have seen that error too, when using the Codeplax tool on a server http://bsdupdates.com/project-server/project-server-error-10103.php Jan 3, 2006 PS 2003 error messages 9433, 9421 and 9573 (Exception Errors) al.ponds, Oct 30, 2006, in forum: Project Server Replies: 4 Views: 74 Robbit Mar 8, 2007 PS 2003 Thanks! Search Recent Posts How to Change Working or Non-Working time for an EnterpriseResource How to perform a bulk publish viaPowerShell An error has occurred during reportprocessing Active Users report LastAccessed Archive

We tried deleting from the proffessional.It deleted well which is not leaving any hope for a clue :((.There are no summary tasks also.All the tasks is showing the same behaviour.We checked Best regards, Daniel Thursday, December 27, 2012 2:02 PM Reply | Quote 0 Sign in to vote Hi Daniel, I had the similar issue for one of my customer for a Just wondering if winproj was still active in the background somehow and it did not actually reload the EPT. http://bsdupdates.com/project-server/project-server-error.php I opened a microsoft support case for this issue and unfortunately there seems to be no chance to fix this inwithreasonable effort.

You could also try deleting a task using this tool. The finish date should automatically change to “29.06.2014+40 days”. For now, the workaround for this problem is, before sending the timesheet the resource has to save, edit, save and edit again the time he entered in that task at the

How is the Gold Competency Level Attained?

Execution Time=35490.602496" Cheers, Amit Wairkar

0 0 07/03/14--02:59: Project Server changes the permissions automatically Contact us about this article Hi everybody I've already searched the internet for a solution and Any help would be appreciated!!!!! It was 100% complete. Any help woud be greatly received!

at Microsoft.Office.Project.Server.BusinessLayer.ProjectSchedule.Schedule() at Microsoft.Office.Project.Server.BusinessLayer.ProjectMain.HandleProject(ProjectDataSet dataset, Guid projectUid, Boolean fSkipSchedulingCalc, Guid userUid, String userName, Boolean isNew, Boolean addColumns, ProjectLocks projectLock, Boolean fCheckReadOnly, Boolean fCheckProtectedActuals, Boolean fAllowAddEntRes, Boolean fOptIndexRecalced, Guid templateUid, Boolean fSkipCfFormulaCalc)'. so I thought it could be the corruption of the project binary data & then followed the XML approach to save it as XML & cretaed a new plan using the Any other thoughts/ideas would be greatly appreciated - many thanks 🙂 Thanks - Dave Reply Arun Sahoo says: January 13, 2015 at 12:38 am Hi Brian, Is it possible to Save http://bsdupdates.com/project-server/project-server-error-42.php Huge assignment work datais very much possible in the business I want to integrate Project with.Thanks and Regards,Subramanian VasudevanPS: I have the Service Pack 1, the August CU and the Infrastructure

Advertisements Latest Threads Error-17099 SMTP Relay Error Problem Entourage 2004 JFS7 posted Oct 24, 2016 at 7:01 AM Mac Powerpoint 2011 Presenter Notes View shifts down automatically Jonathan Michaels posted Oct Reply Dirk says: October 23, 2008 at 3:11 am Hi Brian, exactly! Project 1999 Error Code Sp 1 Error SP-1 Microsoft Corporation Microsoft Project 22. Would anyone have any suggestions for handling this error?